Johnson Custom Home Build

1247 Thornton Creek Drive, Thornton, CO 80241

Started: January 14, 2026
Expected completion: August 14, 2026
📐

Design Phase Complete

completed

Architectural plans finalized and approved

Due: February 27, 2026
Completed: February 24, 2026
✓ Phase completedOn time
🏗️

Foundation Pour

completed

Foundation and basement walls completed

Due: March 20, 2026
Completed: March 17, 2026
✓ Phase completedOn time
🔨

Framing Complete

in progress

Structural framing and roof installation

Due: April 14, 2026
Currently in progressPhase 3 of 8
This phase is actively being worked on. Expect regular updates and progress photos.

Electrical Rough-In

pending

Electrical wiring and panels installed

Due: April 30, 2026
🚿

Plumbing Rough-In

pending

Plumbing lines and fixtures roughed in

Due: May 7, 2026
🎨

Drywall & Paint

pending

Interior walls finished and painted

Due: June 14, 2026
🎨

Flooring Installation

pending

All flooring materials installed

Due: June 30, 2026

Final Walkthrough

pending

Final inspection and client walkthrough

Due: August 9, 2026

Timeline Summary

Overall project progress and key dates

2
Phases Complete
1
Current Phase
5
Upcoming Phases
Overall Progress25%